Project Name: Kipp School
Project Address: 2720 Jerome Ave, Bronx, NY 10468
Owner: Kipp NYC Properties
Construction Manager/General Contractor: Suffolk Construction
Geotechnical Engineer: MFS Engineers
Structural Engineer: Silman
Construction Dates: July 2021 to November 2021
Major Technologies: Drilled Soldier Piles / Rock Anchors / Concrete Buttons
Project Summary:
- This project consists of a 7-story charter school on a 22,000 SF site surrounded by occupied buildings and TA structures.
- CCJV’s scope included excavation of soil and rock, foundation concrete, SOE, and waterproofing.
- Installed approximately 100 tons of rebar.
- Installed approximately 1500 cy of concrete.