New York Presbyterian – Brooklyn Methodist Hospital – Center for Community Health

Project Name: New York Presbyterian – Brooklyn Methodist Hospital – Center for Community Health
Project Address: 515 6th Street, Brooklyn, NY 11215
Owner: New York Methodist Hospital
Construction Manager/General Contractor: Lend Lease
Geotechnical Engineer: Langan Engineering
Structural Engineer: Severud Associates
Construction Dates: November 2016 to September 2017

Major Technologies: Secant Piles / Soldier Piles / Tiebacks / Shotcrete

Project Summary:

  • This project consists of an 8-story hospital on a 2 acre lot bordered by active buildings and streets.
  • CCJV’s scope consisted of excavation, foundation concrete, secant piles, soldier piles, waterproofing
  • Excavated approximately 80,000 cy of soil
  • Installed approximately 500 tons of rebar
  • Installed approximately 6,200 cy of concrete
  • Installed 450 plan LF of secant walls to accommodate excavation next to active buildings.
  • Managed multiple subcontractors to efficiently and safely complete the project on time